PROJEKTABLAUF KITABAU

Here you will find a simplified representation of a typical process of building a day care centre. The project schedule of building a day care centre gives you an overview of all baukind services. Depending on the project status, all services can also be assigned separately.

Phone
INQUIRY

You send us your inquiry. With or without a property or building – with or without existing legal status of your company. We would be pleased to advise you, no matter where you are at in the project.

Lupe
FIRST ADVICE / FIRST REVIEW

We inspect the building or the property site and advise you on construction costs, construction times and options for construction.

baukind-symbol-Haus-Lupe-2
PROPERTY SEARCH

If necessary, we can help you find a suitable property and carry out a suitability test.

Megaphone
CONTRACTING

After a positive feasibility study, you commission us to carry out the necessary services.

baukind-symbol-moebel
FURNISHING BY BAUKIND

If desired, baukind also takes care of the planning and furnishing of your kita – from the mattress platform through to the toothbrush cup.

Kopf
PROJECT MANAGEMENT

After the commissioning, we create a team for the project and you will personally be able to contact the project manager for all your questions and concerns throughout the project period.

Machbarkeit
LPH 1
BASIC EVALUATION / FEASABILITY STUDY

In this phase, we examine the suitability of the property or the existing real estate. We check the eligibility on the basis of local authorities requirements and other authorities concerned, clarify questions about financing and funding and examine the implementation periods.

 

Map
LPH 2
PREPLANNING / FIRST DRAFT OF FLOOR PLAN

The main elements of this phase are the preliminary design of the floor plan and the estimation of costs. This allows for targeted coordination with the authorities, the defining of specifications and negotiations with contract partners. Now the basic decisions can be made as to whether and in what context a project can be implemented.

Lineal-Stift
LPH 3
DRAFT / COSTINGS

Next comes the final draft. Based on the anticipated services, necessary changes are incorporated and the ground plan can be further developed. At this point the costs can be precisely determined: Each construction component with its respective quantities is presented in the “cost calculation”. Due to our experience in more than 60 construction projects, we have a very high level of costing accuracy. The calculation generated in this phase, serves as a basis for the funding application.

Bauantrag
LPH 4
PLANNING APPROVAL / APPLICATION FOR CONSTRUCTION

In this phase, the application for building is submitted. The preparation of all necessary documents for the permit procedure is the essential part of our work at this time. The fire protection concept must also be submitted with the application for building. The fire protection concept is drawn up by baukind itself or an external fire protection engineer. In both cases, the fire protection concept is a separate element that is not included in the basic architectural services.

Planung
LPH 5
PLAN OF EXECUTION

In the execution planning, all plans are prepared in such a way that they provide a basis for the construction work. The ground plans will be further developed and supplemented by detailed drawings, taking into account the final design and materials.

Vertraege
LPH 6
PREPARING THE CONTRACTING / DIRECTORY OF SERVICES

All the architectural details created in the previous phase are now technically drawn in a so-called “directory of services” and allotted to individual trades. Construction contracts are also being prepared at this time. Everything is then either publicly posted or sent to selected companies to obtain offers for all construction services.

Stift
LPH 7
IMPLEMENTATION OF THE ALLOCATION/ EXECUTION OF CONSTRUCTION WORK

When all offers from the individual trades become available, the “allocation” takes place. The offers will be checked and the most economic offer will be assigned. The contracts for construction are closed and the construction schedule is prepared.

Uhr
LPH 8
OBJECT SURVEILLANCE/ CONSTRUCTION SITE MANAGEMENT

Now the construction phase begins. We as architects are responsible for the supervision and control of all work to be carried out, in order to ensure a smooth construction process and an appropriate completion date.

baukind-symbol-moebel
FURNITURE / INTERIOR FITTINGS

At this time, the furniture and fittings are delivered.

Dokumentation
LPH 9
DOCUMENTATION

We offer this service phase only upon request for larger construction projects. It includes the monitoring and ascertainment of construction defects in the 5 years following completion, as well as the additional documentation of the construction project.

Schluessel
OPENING / APPROVAL FROM THE ADMINISTRATIVE OFFICES

We accompany you through the entire construction project up until the opening. Also we assist you through the authorization process by the administrative offices. Congratulations on opening your day care center!